"Admiral Kuznetsov (063)" ??
Only Russian aircraft carrier, has suffered several mishaps during its modernization.
The process would have begun in October 2017 at Murmansk Shipyard, due to end in 2020, a budget of $ 890 million had been allocated to fully renew it.
But as early as February 2018 due to budget problems was cut by 50 %, but the final strike was when in October of the same year a 70-ton crane broke down and led to the collapse of the floating PD dam - 5.
In December 2019 a fire suffered, its modernization continues.
Could be delivered in 2024.